
Construction of Global Tech I wind farm off German coast in 2013
To support the Paris Agreement’s goal of limiting temperature increase to 1.5°C, Europe will need a CO2-neutral electricity supply by 2045. A target we cannot meet unless we ramp up Europe’s offshore wind capacity, says Michiel Müller from consultancy Ecofys, a Navigant company. The company’s energy experts calculated that the current offshore wind installation rate would have to triple to get this goal within reach. They argue that an integrated North Sea Grid is the only way to achieve this growth at lowest possible cost while maximizing benefits to the environment.
To meet the goal agreed at the Paris climate change conference in December 2015, Europe will need a fully decarbonized electricity supply by 2045.
Renewables are essential to making this happen. The joint energy team of Ecofys and Navigant have investigated Europe’s renewable generation resources and find that offshore wind from the North Seas region will be pivotal for realising a 100% decarbonised electricity supply in less than 30 years.
In their analysis, the experts looked specifically at the ten countries around the North Sea – France, Belgium, the Netherlands, Luxemburg, Germany, Denmark, Sweden, Norway, Ireland, and the United Kingdom – that cooperate in the EU-supported North Seas Countries Offshore Grid Initiative established in 2009.
Such growth in offshore wind cannot be realised through individual efforts—it is possible only through a new level of collaboration, coordination, and interconnectivity between the North Seas countries
To determine the required offshore capacity for the whole region, the team started with the 2045 electricity demand per country and assumed a complete phaseout of fossil-fueled electricity generation, as well as a started retirement of nuclear. We assumed that current operational nuclear plants will be decommissioned and not replaced after their lifetime. Thus, the only nuclear plants around by 2045 will be new ones that are in an advanced planning stage today.
The Ecofys and Navigant consultants then determined the total available onshore generation capacity by means of several scenario studies and identified how much of the Paris-compatible electricity generation capacity can be met on land. The countries’ joint onshore generation resources (wind, solar, bio, hydro, and remaining nuclear)could provide up to 55% of the required capacity. This leaves 45% to be covered by offshore sources and translates into an offshore wind target of approximately 230 GW for the North Seas countries. [ 180 GW of that capacity could be generated in the North Sea, and the remaining 50 GW in other seas like the Baltic and Irish Seas and the Atlantic.
With 13 GW installed currently, however, the region is far from the required total. To realise this growth, the offshore wind installation rate would have to triple from the current 3 GW/year to approximately 10 GW/year in 2030.
Long-term spatial planning
Such growth in offshore wind cannot be realised through individual efforts—it is possible only through a new level of collaboration, coordination, and interconnectivity between the North Seas countries. In addition to its role as a natural habitat, the North Sea is intensely used as a place for fisheries, tourism, military zones, oil & gas infrastructure, and shipping, and therefore of vital importance to the region’s economy.
While there is sufficient space to develop the required offshore wind capacity (current estimates indicate that some 10% of the North Sea surface will be required for offshore wind, based on a wind farm intensity of 5-6MW/km2), a careful balance must be maintained, ensuring maximum benefit to the environment and cost-efficient development of both wind farms and associated infrastructure.
The analysis shows that Great Britain and Ireland have a need for import capacity of roughly 30 GW, while continental North Western Europe has a deficit of 25 GW
Harnessing and preserving the environment of the North Sea region requires constructive collaboration among all sectors. The potential offshore grid could support the marine biodiversity through new protected areas for wildlife and extended migratory corridors.
This requires a shared long-term view by all North Sea countries. A joint spatial planning strategy is needed to reflect changes in use (e.g., decommissioning of oil & gas) and ensure a cost-efficient utilization of the resource, aligned with offshore and onshore grid development and environmental protection.
50 GW-80 GW interconnector capacity required for grid balancing
Long-term planning will also have to go into securing the stability of such new infrastructure. With higher shares of renewable energy, the stability of the grid heavily depends on an increase in flexibility options. A crucial enabler for a flexible power system is a well-developed network, or in the case of the North Sea offshore wind-dominated system, an infrastructure with increased levels of interconnectivity.
Based on a high level adequacy assessment, we determined the likely reliable capacity that would be available. Ecofys investigated peak demand situations for the three sub-systems around the North Sea: Great Britain and Ireland, continental Northwestern Europe, and the Nordics.
The team analysed how much wind power is available at minimum wind conditions with regard to climatic data and the geographical spread of wind parks. Comparing the results with the available onshore resources, dispatchable generation and flexibility from demand and storage, they deducted the margin each of the three ‘sub-systems’ has. A negative margin shows a need to interconnect to regions with more resources.
With the phaseout of fossil-fueled electricity generation the dispatchable generation capacity drops from a level of 64% in today’s generation mix to approximately 25%
The analysis shows that Great Britain and Ireland have a need for import capacity of roughly 30 GW, while continental North Western Europe has a deficit of 25 GW. An overall level of 50 GW-80 GW of interconnection capacity will be required for the North Seas area.
Growth of interconnection capability requires a careful evaluation of the cost-benefit analysis approach. A new methodology to value grid stability could incentivize interconnector capacity. Current planning practice often limits the level of offshore interconnections to save operational costs. Today’s main methodology, approved by regulators and the European Commission, compares the cost for a new interconnector with the carbon and fuel cost savings it will bring about.
After 2030, these savings will be less of an incentive when renewables plants – with zero marginal and no carbon costs – are dominating the market. Interconnectors, however, will still be crucial as they give flexibility in stressed system conditions and periods of scarcity, and thus provide security of supply. The current methodology does not express this benefit. The task therefore demands a new way of thinking: business cases will have to be redefined to include societal and environmental profits.
More flexibility options
The transition to a decarbonised electricity supply marks the end of dependence on conventional reserves. This will also mean a significantly reduced dispatchable capacity and calls for a steep increase in flexibility options.
With the phaseout of fossil-fueled electricity generation, the dispatchable generation capacity drops from a level of 64% in today’s generation mix to approximately 25%, primarily from hydro and bio, in the 2045 system.
A transition to new, cost-effective flexibility sources such as storage, demand response, power-to-gas/heat, and ancillary services from renewables is already underway. The use of these new flexibility sources will become essential in the 2045 scenario to ensure a constant, instantaneous supply/demand balance.
Developing a long-term spatial planning strategy and a robust 2045 roadmap for flexibility options will be two of the key steps to meeting the Paris goals
This means that a more realistic and robust potential estimate and roadmap are needed than currently available forecasts, to plan demand response, small-scale storage and large-scale storage by 2045. This should not be based purely on industry-push figures, but also on making the tradeoff of some of these projects with interconnection levels. With flexibility options becoming both more significant and affordable, e.g., the demand for interconnection could go down and in turn further increase the need for flexibility options.
However, before this demand can be addressed on the technical level, it will be the collaborative connection between the involved countries and public and private stakeholders that counts.
Developing a long-term spatial planning strategy and a robust 2045 roadmap for flexibility options will be two of the key steps to meeting the Paris goals. Joint strategic planning will secure operational security during and beyond the energy transition.
Editor’s Note
Michiel Müller is a Managing Director at Ecofys, a Navigant company, and an offshore wind energy expert. He has published two white papers on the topic and presented the above findings at the European Commission’s North Seas Energy Forum 2017. Find the full presentation here.
[adrotate banner=”78″]
What I miss here is some context on how this would fit into the larger European power system. Surely the author is not proposing that the North Sea area could (and should) have a fully self-contained renewables grid? Note for example the recent and much quoted article from Nature Climate Change which discusses integration of wind and solar from the Balkans. I guess that the author is trying to say that local storage, power to heat, etc., will make the large scale interconnections less important, but he is very vague about what this would really mean.
Thanks, S. Herb! The North Sea offshore energy generation indeed serves the wider European energy system. European countries are moving towards more regional ambitions and further integration of markets; and our model did take into account connections with South and Eastern Europe. Also flexibility providers (demand response, storage, power-to-heat, interconnection) all have potential, and can thus be seen as competing solutions. For further insight in the balance of these options, see our recent full report which gives more insight: http://www.ecofys.com/files/files/ecofys-2017-translate-cop21-offshore-wind-north-seas.pdf
I went quickly through your report and there is really not any substantive information on the relation between the North Sea area and the rest of Europe. I do agree that it is important to do a good job on setting up the regional networks before going into details on longer range power transfer and the tradeoffs vs. flexibility and local and intra-regional storage. Nonetheless I am unhappy not to have some rough estimates for, say, the fraction of the total TWh that is not met by instantaneous wind generation, and the fraction which must be curtailed, lacking storage or export capabilities. These are very basic numbers.
The Balkans would need photovoltaics but there is a financing issue and investors hesitate to get in due to legal risks. What it means to fully rely on renewables without a smart mix and cost reflective tariff structure can be seen in Albania nowadays. The current news about the energetic situation in the country should be read also in mind of the adequacy reports:
MIA, 08 August
Similar news: novamakedonija.mk, tvnova.mk, plusinfo.mk, a1on.mk, lokalno.mk, ohrid1.mk, vecer.mk, start.mk,
Vecer, Nova Makedonija
ALBANIA COVERS 80 PERCENT OF ITS ELECTRICITY NEEDS FROM IMPORT
Due to the severe drought period Albania satisfies up to 80% of its electricity needs from imports. The level of the
largest power plant on the cascade of the river Drim, “Fierza”, which is the second largest hydropower plant in the
Balkans after “Djerdap” on the Danube River, fell below the minimum utilization level and operates with a minimum
capacity. As the MIA correspondent reports, because of the drought period, the production in the other two
hydroelectric power plants on the river flow of the river Drim, “Koman” and “Vau i Dejes”, is minimal. Therefore, the
Albanian Power Corporation (KESH) is forced to import additional 30 thousand megawatt hours, which is conditioned
by the increased consumption due to the very high temperatures. Earlier, KESH agreed to import 434 thousand
megawatt hours of electricity worth EUR 29.9 million in August. Albania started the import of electricity in larger
quantities in July, when more than 285 thousand megawatt hours of electricity were imported, worth EUR 18
million. KESH said that if the drought continues, next month the country will completely depend on the import of
electricity. In such circumstances, the supply of electricity will exceed the financial capabilities of the company,
which will require the government to intervene with budget funds.